Hilcorp, Alaska LLC; Dan Polito, states the purpose is to satisfy the Pipeline and Hazardous Material Safety Administration (PHMSA) compliance order and allow the Middle Ground Shoal (MGS) to continue producing oil and gas, as well as decreasing the future likelihood of fatigue or abrasion leaks on these pipelines. The applicant proposes to lay 6.49 miles of dual (2) new 8” diameter pipelines from the MGS platform A to the MGS onshore facility, below the Mean High Water Mark (MHW) of the Cook Inlet (19.7’ above the 0.0’ contour) for the purpose of transporting oil and gas. The project site is located within Section 34, T. 8 N., R. 12 W., Seward Meridian; USGS Quad Map Kenai C-4 and D-4; Starting at Latitude 60.7368º N.,
Longitude 151.3490º W and ending at Latitude 60.7946º N., Longitude 151.4978º W.; near Nikiski, Alaska. Please contact Andrew Gray at (907) 753-2722 or by email at Andrew.a.gray@usace.army.mil if further information is desired concerning this notice.