North Slope Borough's stated purpose is to increase the existing capacity of SA10 landfill. The landfill expansion would ensure uninterrupted solid waste disposal for the area. To place 352,391 cubic yards of gravel material in 51.70 acres of palustrine wetlands to construct two (2) new landfill cells, gravel-support pad, perimeter access road, and snowmelt/storm water swale. Acreage and volume of fill material estimated for each of the project components are shown in the table below. Gravel source will come from an approved gravel source. All work would be performed in accordance with the enclosed plan (sheets 1-7), dated January 27, 2014. Please contact Estrella Campellone at (907) 753-2518, toll free from within Alaska at (800) 478-2712, by fax at (907) 753-5567, or by email at Estrella.f.campellone@usace.army.mil if further information is desired concerning this notice.
POA-2014-148, Putuligayuk River_PN
POA-2014-148, Putuligayuk River_PN Drawings