In 2021, the district awarded the contract to Bauer Foundation Corp. of Florida and construction began in May 2022. The two machines atop the dam, a cutter soil mixer and an auger, are being used to mix the existing gravel inside the structure with cement and bentonite to depths up to 65 feet. This work will address the risks of aging infrastructure and extend the life of the structure for many years to come. The project is scheduled for completion in January 2026 and the total estimated value of the work is about $148 million.