US Army Corps of Engineers
Alaska District Website

Public Notice Manager

Results:
Archive: 2017
Clear
  • POA-2008-782-M4

    Expiration date: 9/6/2017

    The City and Borough of Juneau stated the purpose is to improve safety, increase efficiency and reduce congestion by increasing harbor efficiency through safe access to the harbor, improving pedestrian access, reducing congestion and separating user groups. The project site is located within Section 23, T. 40 S., R. 65 E., Copper River Meridian; USGS Quad Map Juneau B-2; Latitude 58.385º N., Longitude 134.646º W.; Don D. Statter Harbor, in Juneau, Alaska. The applicant requests authorization for the following work in waters of the United States, including navigable waters: -From below the Mean High Water Mark ((MHW) approximate elevation +15.3 feet above the 0.0 foot contour) demolish and dispose of the existing 16 feet wide by 200 feet long concrete boat launch ramp and planks; -From below the MHW demolish and dispose of the existing 8 feet wide by 240 feet long timber boarding float, including (4) 12.75 inch diameter steel pipe piles; -From below the MHW demolish and dispose of the existing 1,152 square feet timber boat haul-out pier, including (16) creosote treated timber piles. -Dredge approximately 24,300 cubic yards of marine sediment from 1.47 acres below the MHW to provide sufficient water depth for vessels at all tidal ranges. The disposal of 30,375 cubic yards of dredged material (increase due to bulking factor) is proposed through the discharge over 65 acres of the seafloor at a location approximately 1 mile southwest of the proposed dredging site at Latitude 58.3728º N., Longitude 134.6637º W. in Auke Bay; -Remove by blasting 2,000 cubic yards of bedrock from 0.27-acres below the high tide line ((HTL) approximate elevation +20.6 feet above the 0.0 foot contour) and MHW; -Install below the MHW one 12 feet wide by 240 feet long concrete main float with five 6 feet wide by 42 feet long finger floats; -Install below the MHW one 16 feet wide by 180 feet long timber main float; -Install below the MHW one 16 feet wide by 140 feet long timber main float; -Install below the MHW one 16 feet wide by 226 feet long timber headwalk float; -Install below the MHW one 20 feet wide by 20 feet long gangway landing float; -Install below the MHW on 8 feet wide by 110 feet long aluminum gangway; -Install below the MHW (20) 16-inch diameter steel pipe piles, (6) 24-inch diameter steel pipe piles; -Discharge 8,800 cubic yards of shot rock and armor rock fill and 2,496 cubic yards of concrete planks into 0.45 acres below the HTL to construct a 12 feet wide by 208 feet long kayak launch ramp; -Discharge 1,350 cubic yards of armor rock fill material into 0.42-acres below the HTL to stabilize the dredge basin side slopes; -Temporary placement of 12,500 cubic yards of 4-inch minus shot rock fill into 0.75-acres below the HTL to construct a drill pad to place explosive charges for bedrock removal. All work would be performed in accordance with the enclosed plan (sheets 1-14), dated May 2017. Please contact Randal Vigil at (907) 790-4491, or by email at Randal.P.Vigil@usace.army.mil if further information is desired concerning this notice.

  • POA-2003-598

    Expiration date: 9/5/2017

    ASRC Civil Construction, LLC's stated purpose is to expand the existing gravel pit to procure enough gravel to support the Golovin Airport Improvement Project. The project site is located at Latitude 64.56243º N., Longitude 163.01172º W.; from the Golovin Airport head north for approximately one mile on Nichols Street and the gravel pit is on the east side of the road near Golovin, Alaska. Excavate a 300 foot by 300 foot area (2.1 acres) in palustrine wetlands at the north end of the gravel pit to extract 30,000 cubic yards (cy) of gravel. The Material would be processed and stockpiled within the pit until hauled to project sites. All work would be performed in accordance with the enclosed plan (sheets 1-3), dated July 11, 2017. Please contact Jason Brewer at (907) 753-2823, toll free from within Alaska at (800) 478-2712, by fax at (907) 753-5567, or by email at Jason.D.Brewer@usace.army.mil if further information is desired concerning this notice.

  • POA-2003-1238-M4, Chena Slough

    Expiration date: 8/30/2017

    PURPOSE: PBJ Enterprises LLC’s stated purpose is expansion of an existing commercial gravel source to meet existing and projected need for development projects in the greater North Pole area. LOCATION: The project site is located within Section 5, T. 2 S., R. 2 E., Fairbanks Meridian; USGS Quad Map Fairbanks D-1; Latitude 64.7717º N., Longitude 147.3905º W.; Quinnell Subdivision, State Tax Parcel ID Pan 626993, TL -541, North Pole, Alaska PROPOSED WORK: Under permit ID, POA-2003-1238-M2 and POA-2003-1238-M3, the existing access road and manmade lake, (3.4 acres- existing commercial gravel source), was permitted on August 26, 2005 and August 31, 2015, respectively. The proposed project is to expand the existing gravel source area to dredge and stockpile approximately 70,000 cubic yards of material, which would impact 21.2 acres of wetlands. Overburden would be removed and stockpiled to make landscaping soil mix with the remaining overburden used for reclamation. The dredge area would be cleared first, with the eventual development of the entire lot, except for 10’ wide undisturbed buffers on the east and west borders of the lot, and a 200’ wide natural area on the north end of the lot. Overburden removal is planned to start September 1, 2017 with dredging operations to begin April 1, 2018. Expected timeframe for material extraction and stockpiling is 20 years. More detailed information, alternative analysis, and the mining plan are presented on enclosed sheets 1 and 2. All work would be performed in accordance with the enclosed plans, (sheets 1-7), dated 6/19/2017. Note: The Corps of Engineers does not consider a 20 year operation temporary even though the applicant plans to reclaim and naturalize material site after operations are complete. Comments on the described work, with the reference number, should reach this office no later than the expiration date of this Public Notice to become part of the record and be considered in the decision. Please contact Melissa Riordan at (907) 474-2166, by fax at (907) 474-2164, or by email at melissa.c.riordan@usace.army.

  • POA-2017-184

    Expiration date: 8/30/2017

    Isadora Fanning (Alaska Department of Transportation and Public Facilities (ADOT & PF)) stated the purpose is to improve safety and efficiency of the Kiana Airport by bringing the airport to Federal Aviation Administration (FAA) standards for aircraft delivering essential goods and services to the community. The project is located at the Bob Baker Memorial Airport, Latitude 66.9758333, Longitude – 160.4363888, Kateel River Meridian, T18N/19N, R8W/8W, S 4,5,6,8,9 / 31,32 near the community of Kiana, Northwest Arctic Borough, Alaska. The proposal involves various airport improvements, including skewing and lengthening the existing runway and taxiway, expanding the existing apron, resurfacing operational surfaces, and replacing light and navigational aids (NAVAIDs). Gravel will be sourced from a new, offsite gravel pit located approximately 2.8 miles to the northwest of Kiana, and accessed via a proposed permanent gravel road. The proposed work will result in the filling of 113.99 acres of wetlands, of which 92.82 acres of wetlands will be filled permanently and 21.17 acres will be filled temporarily. Total volume of fill is 304,441 cubic yards. Please contact Mr. Steve Moore by email at stephen.a.moore2@usace.army.mil, by phone at (907) 753-5713, toll free from within Alaska at (800) 478-2712, or by fax at (907) 753-5567 if you have questions or need further information concerning this public notice.

  • POA-2016-44

    Expiration date: 8/30/2017

    Charlie Carpenter (Arctic Slope Telephone Association Cooperative, Inc. (ASTAC)) stated the purpose is to “fill approximately 1.5 acres of wetlands for the construction of a gravel pad. Initially, the gravel pad would be used for equipment and material storage. Ultimately, the pad would be used as the operations center for ASTAC’s Barrow business unit, and include a warehouse (3,600 square foot), crew living quarters (5,000 square foot), and administrative offices and equipment building (3,500 square foot).” The project site is located at Latitude 71.27472º N., Longitude 156.80741º W.; from the Wiley Post-Will Rogers Memorial Airport head west until you reach Apayauk Street, then turn left and follow the road south around the end of the runway for approximately 0.5 miles to Nunavaaq Road and turn right. Continue southwest for approximately 0.5 mile and the project site is on the south side of the road in Barrow, Alaska. The applicant proposes to discharge 7,025 cubic yards of fill into 1.5 acres of palustrine wetlands to construct a gravel pad for an operations center. All work would be performed in accordance with the enclosed plan (sheets 1-3), dated July 11, 2017. Please contact Jason Brewer at (907) 753-2823, toll free from within Alaska at (800) 478-2712, by fax at (907) 753-5567, or by email at Jason.D.Brewer@usace.army.mil if further information is desired concerning this notice.

Jump To:

Redirecting...